CE 2.5: Defective Caulking

Performance

Caulking should be installed in accordance with manufacturer’s specifications. Caulking shall remain intact without de-bonding, cracking/splitting or showing other signs of premature strain within the warranty period. Profiling of caulking should accommodate anticipated movement at the sealed joint. Caulking must cure as anticipated in the manufacturer’s specifications. All joints shown in the design to be caulked shall be caulked.

Warranty

One-Year - Work and Materials. One-Year – Ontario Building Code Violation. Two-Year – Cladding Detachment, Displacement or Deterioration. Damage resulting from improper maintenance is not covered by the statutory warranty

Action

Caulking which does not achieve the specified performance requirements shall be repaired.

Article number
2.5
Article type
Common Element
Warranty years
One Year
Two Year
Article title
Defective Caulking

CE 1.3: Leakage Through Suspended Parking Slabs And Ramps

Home type
Performance
Suspended parking slabs including suspended ramps shall be protected by a material/substance to prevent water penetration and leakage and to protect the slab from exposure to chlorides in accordance with the Ontario Building Code including CSA 413 and the design.
Warranty
One-Year – Work and materials. Two-Year - Building Envelope Water Penetration
Action
The waterproofing membrane not meeting acceptable performance shall be repaired to prevent leakage.
Article number
1.3
Article type
Common Element
Warranty years
One Year
Two Year
Article title
Leakage Through Suspended Parking Slabs And Ramps

CE 2.4: Corrosion Of Coated Metal Elements

Performance

Protective coatings shall remain intact and effective for the warranty period. Protective coatings shall remain free of corrosion.

Warranty

One-Year - Work and Materials

Action

Corroded materials, corrosion shall be removed and the substrate refinished with appropriate protective coating.

Remarks

This item is not intended to address corrosion related to chips or other post-installation damage, but rather material failure of the paint finish. Components which are specified to be shop primed will be expected to corrode, and corrosion of these elements is not warranted.

Article number
2.4
Article type
Common Element
Warranty years
One Year
Article title
Corrosion Of Coated Metal Elements

CE 2.24: Movement Joints In Masonry Are Obstructed

Performance

Movement joints in masonry construction shall allow free movement of masonry to prevent or relieve stress due to differential movement.

Warranty

One-Year - Work and Materials

Action

Movement joints not meeting the Acceptable Performance shall be repaired.

Remarks

The Ontario Building Code references CSA A371 “Masonry Construction for Buildings”

Article number
2.24
Article type
Common Element
Warranty years
One Year
Article title
Movement Joints In Masonry Are Obstructed

CE 2.23: Draft Felt At Electrical Outlet

Performance

Electrical boxes on exterior walls that are installed in the plane of the air barrier system shall be installed to prevent air infiltration.

Warranty

One-Year - Work and Materials. Damage resulting from normal wear and tear, improper maintenance or additions, alterations and deletions made by the homeowner is not covered by the statutory warranty.

Action

Electrical boxes not meeting the acceptable condition shall be repaired.

Remarks

Some drafts may occur around electrical outlets or receptacles on exterior walls, particularly when it is cold or windy. Convection air movement may simulate draft conditions.

Article number
2.23
Article type
Common Element
Warranty years
One Year
Article title
Draft Felt At Electrical Outlet

Common Element 2.22: Discontinuity In Air Barrier System

Performance

The air barrier system shall meet the requirements of the Ontario Building Code.

Warranty

One – Year- Work and Materials. One – Year – Ontario Building Code Violation. Two – Year- Health and Safety. Damage resulting from improper maintenance or additions, deletions or alterations made by the homeowner is excluded from the statutory warranty.

Action

Air barrier systems not in accordance with the acceptable condition shall be repaired.

Remarks

Continuity of the air barrier is important to maintain acceptable conditions for building occupants to minimize the accumulation of condensation within the assemblies, to control heat transfer to roofs where ice damming occur and to allow proper operation of the building services.

Article number
2.22
Article type
Common Element
Article title
Discontinuity In Air Barrier System

CE 2.21: Weep Holes Missing in Masonry Exterior Cavity Wall or Veneer System

Performance

Weep holes in masonry veneer shall be installed to achieve the performance required by the Ontario Building Code.

Warranty

One --Year- Work and Materials. One – Year – Ontario Building Code Violation

Action

Masonry veneer not meeting the acceptable condition shall be repaired.

Remarks

The Ontario Building Code references CSA A371 “Masonry Construction for Buildings”; section 12 discusses requirement for weep holes.

Article number
2.21
Article type
Common Element
Article title
Weep Holes Missing in Masonry Exterior Cavity Wall or Veneer System

CE 2.2: Exposed Balcony Concrete Finishes have Excessive Variation in Colour

Performance

Variations in concrete colour are to be expected with cast-concrete construction. Variations are considered acceptable if the finishes provide a general uniformity in appearance when viewed from grade.

Warranty

One-Year - Work and Materials

Action

Concrete with excessive variation in colour shall be cleaned or coated to provide a uniform finish.

Remarks

Cast concrete will inherently have colour variations. While upgraded finishes are possible, they are not mandatory and are at the discretion of the design team. There are no requirements in the Ontario Building Code to paint the surface. However, if the builder does apply paint (of the appropriate type) to the surface the warranty shall apply to the installed paint.

Article number
2.2
Article type
Common Element
Warranty years
One Year
Article title
Exposed Balcony Concrete Finishes have Excessive Variation in Colour

CE 2.19: Condensation Forming Between The Panes Of An Insulating (Factory Sealed) Glass Unit

Performance

Insulating glass units shall be free from condensation between the panes.

Warranty

One-Year -Work and Materials

Action

Insulating glass units with condensation between the panes shall be replaced.

Remarks

Condensation between panes indicates the airtight seal around the edge of the glass is broken. An extended warranty may be available through the window manufacturer.

Article number
2.19
Article type
Common Element
Warranty years
One Year
Article title
Condensation Forming Between The Panes Of An Insulating (Factory Sealed) Glass Unit

CE 2.18: Construction Material Splatters and Stains

Home type
Performance

The building shall not have splatters and/or stains relating to construction materials which detract from the appearance of the building when viewed from a distance of 6m. For balconies, terraces etc where a 6m viewing distance is impractical then the condition shall be assessed from a normal viewing position.

Warranty

One – year – Work and Materials

Action

Conditions not meeting the acceptable condition shall be repaired.

Remarks

Some minor splatters in areas of the building which are not routinely occupied (e.g. mechanical penthouse) and which are not visible from routinely occupied areas may be considered acceptable.

Article number
2.18
Article type
Common Element
Article title
Construction Material Splatters and Stains